Upon receiving all necessary permits, construction activities for this project are expected to begin by spring/summer 2027. These activities will include mobilzation of personnel and equipment, site preperation, and installation and testing of new compressor and gas cooling facilities. Construction should be completed by May 2028.
| June 13, 2013 | FERC Application Filed - Docket No. CP13-502-000 |
| June 26, 2013 | FERC Issues Notice of Application |
| July 2, 2013 | Supplement to FERC Certificate Application Filed |
| July 10, 2013 | FERC Issues Notice of Intent to Prepare an Environmental Impact Statement |
| Febraury 12, 2014 | FERC Issues Notice of Availability of the Draft Environmental Impact Statement |
| August 18, 2014 | FERC Issues Notice of Revised Schedule for Environmental Review |
| October 24, 2014 | FERC Issues Notice of Availability of the Final Environmental Impact Statement |
| December 2, 2014 | FERC Order Issuing Certificates and Approving Abandonment |
| February 13, 2026 | Petition for Reissuance of FERC's Certificate Authority Filed - CP13-502-003 |
| February 24, 2026 | FERC Issues Notice of Petition |
To Be Determined
To speak to an Iroquois representative regarding the WIP Project please call:
Ruth Parkins, Government and Stakeholder Relations Director
203-925-7209
Michael Kinik, Senior Director, Operations
203-925-7223