Arrows

Enhancement by Compression Project

A 'Compression ONLY' ALTERNATIVE TO
PROVIDE ADDITIONAL CAPACITY TO NYC

 
 
Iroquois Gas Transmission System, LP (“Iroquois”) is proposing a ‘compression only’ enhancement of its existing system to receive an additional 125 million cubic feet per day of natural gas at Iroquois’ interconnect with the TC Energy Canadian mainline in Waddington, NY for redelivery to New York utilities.  

The ExC Project involves the addition of compression and associated gas cooling at existing Iroquois compressor station sites only.  All new facilities will be constructed entirely within Iroquois’ existing compressor station properties. No new pipeline is proposed as part of this project. 
  brochure

Click to View Brochure

  
 
 

  • Addition of ~12,000 HP of compression and gas cooling at Iroquois’ Athens, NY Compressor Station
  • Addition of ~12,000 HP of compression and gas cooling at Iroquois’ Dover, NY Compressor Station
  • Addition of ~24,000 HP of compression and gas cooling at Iroquois’ Brookfield, CT Compressor Station
  • Addition of gas cooling only at Iroquois’ Milford, CT Compressor Station
  • Installation of Emission Reduction Equipment at Project Sites
  • Proposed In-Service January 1, 2027
 

New York

  • Greater supply to NYC will help alleviate the need for gas moratoriums and benefit economic development
  • Increased supply facilitates conversions from oil heat to gas heat while supplying new construction with natural gas instead of #2 fuel oil
  • Supports the intermittency of renewable energy sources

Connecticut

  • Complements the state’s zero-carbon initiatives and pursuit of off-shore wind resources
  • Reduces price volatility and lowers fuel prices for gas and electric utilities
  • Enhances electric grid reliability and resiliency with additional compression that enables fast start and quick ramping during peak periods
 

Mutual Benefits

  • Additional capacity with no new pipeline
  • Reduction in life cycle GHG emissions and air pollution
  • Increased property tax revenue for host communities
  • Construction jobs and boost to local economy during construction
  • Project related Community Grants
 

The ExC Project filed a formal application with the FERC in late January 2020, and received approval on March 25, 2022.

The FERC, as lead federal agency, made an assessment of the project from an environmental standpoint and issued a determination that the proposed project is within the public convenience and necessity. Additional information on the FERC process can be found at www.ferc.gov and by viewing the brochure: Your Guide to Electronic Information at FERC

Upon receiving all necessary permits, including state air permits, construction activities for this project are expected to begin by fall 2025/spring 2026. These activities will include mobilization of personnel and equipment, site preparation, and installation and testing of new compressor and gas cooling facilities. Construction should be completed by January 1, 2027.

*Revised due to regulatory delays.

 

January 31, 2020 FERC Application Submitted - Docket No. CP20-48-000
February 12, 2020 FERC Issues Notice of Application
March 25, 2020 FERC Issues Notice of Intent to Prepare an EA and Request for Comments
April 3, 2020
April 14, 2020
FERC Issues Notice of Schedule for Environmental Review
Supplemental Filing Appendix 9-E Human Health Risk Assessment
September 30, 2020 FERC Issues Notice of Availability of the Environmental Assessment for the Proposed ExC Project
May 27, 2021 FERC Issues Notice of Intent to Prepare an Enviromental Impact Statement
June 11, 2021 FERC Issues Notice of Availability of the Draft Environmental Impact Statement for the Proposed ExC Project
July 8, 2021 FERC Issues Notice of Revised Comment Period Deadline
September 2, 2021 FERC Issues Notice of Revised Schedule for Environmental Review
November 12, 2021  FERC Issues Notice of Availability of the Final Environmental Impact Statement
March 25, 2022 FERC Order Issuing Certificate of Public Convenience and Necessity 
   
February 28, 2020 Athens NYDEC Air State Facility Permit Application Pkg as Supplemented
  Athens NYDEC State Facility Permit Application Air Dispersion Modeling Report 
February 28, 2020 Dover NYDEC Air State Facility Permit Application Pkg as Supplemented 
  Dover NYDEC State Facility Permit Application Air Dispersion Modeling Report 
January 15, 2021 Athens SO2 Modeling Supplemental Update
January 15, 2021 Dover SO2 Modeling Supplemental Update
May 14, 2021 Iroquois Response to NYDEC RFAI No1 Questions 4-6
October 13, 2021 Iroquois Response to NYDEC RFAI No1 Questions 1-3
April 29, 2022 Iroquois Response to NYDEC RFAI No2 Questions 1-4
November 7, 2022
Iroquois Response to NYDEC RFAI No3 Revised DAC Evaluation 
December 27, 2022 NYDEC Draft ASF Permit for the Athens Compressor Station 
December 27, 2022 NYDEC Draft ASF Permit for the Dover Compressor Station
December 28, 2022
February 28, 2024
March 27, 2024
NYDEC Combined Notice for Iroquois ExC Project
NYDEC Notice for Iroquois ExC Project
NYDEC Notice of Extension for Public Comment Period 
 

 

Date 

Time

Town 

Address

December 2, 2019

Open House Invitation

6:00 PM to 8:00 PM

Milford, CT

Veterans Memorial Auditorium Dressing Room
(Located in the Parsons Government Center)
53 West Main St. 
Milford, CT 

December 3, 2019

Open House Invitation

6:00 PM to 8:00 PM

Brookfield, CT

Brookfield Town Hall
100 Pocono Road
Brookfield, CT 

January 8, 2020

Open House Invitation

6:00 PM to 8:00 PM

Athens, NY

Athens Volunteer Fire Department
39 3rd Street
Athens, NY 

January 9, 2020

Open House Invitation

6:00 PM to 8:00 PM

Dover, NY

American Legion Post 1949
797 Route 22
Wingdale, NY 

 

To Be Determined

 

 

To speak to an ExC Project team member, please call:

Rob Perless, Project Director
203-944-7016

Ruth Parkins, Director, Government and Public Relations
203-925-7209

Michael Kinik, Director, Engineering Services
203-925-7223