BROOKFIELD

Activity

Begin

Anticipated
Completion

Demolition of Existing Building

Mid
November 2007

Completed

Site Preparation (Clear, Fill, Grade)

Early
December 2007

Completed

Foundation

April 2008

June 2008

Construction of Compression Facility

Early
Spring 2008

November 1, 2008

DOVER

Activity

Begin

Anticipated
Completion

Site Preparation

January 2008

Completed

Foundation

April 2008

May 2008

Construction of Cooling Facility

June 2008

September 2008

Scheduled activities are subject to change based on weather and other conditions.

Updated 4/2/08

 