 Notice Status Description:   Supersede
 Prior Notice Identifier:   3501
 Notice Type Description:  Planned Service Outage
 Critical?:  N
 Notice Effective Date/Time:  04/19/2017 09:00:00
 Subject:  Annual Maintenance 2017 - 2018
 Notice Text:
  Pursuant to section 20

Annual Maintenance 2017 – 2018

 

Pursuant to section 20.2a of the Iroquois Gas tariff, listed below are the maintenance projects that are scheduled for the year beginning April 1, 2017 and ending March 31, 2018.

 

Project Description

Affected Area

Outage Time

Duration

Impact

*Brookfield Annual Compressor Maintenance

Zone 2

March 27, 2017 – March 31, 2017

Approx. 12 hours each day.

May affect Primary Firm, Secondary, and IT Transportation/Loan Availability.

Canajoharie Tie In with Dominion Pipeline

Zone 1 and Zone 2

June 10, 2017

Approx. 12 hours

May affect Primary Firm, Secondary, and IT Transportation/Loan Availability.

Boonville Compressor Controls Upgrade

Zone 1 and Zone 2

April 24, 2017 –

May 13, 2017

24 hours each day

May affect Primary Firm, Secondary, and IT Transportation/Loan Availability.

Boonville Annual Compressor Station Maintenance

Zone 1 and Zone 2

May 15, 2017 –

May 23, 2017

24 hours each day.

May affect Primary Firm, Secondary, and IT Transportation/Loan Availability.

Wright Annual Compressor and Station Maintenance

Zone 2

June 5, 2017 –

June 9, 2017

Approx. 12 hours each day.

May affect IT and Secondary Transportation/Loan Availability.

In Line Inspection  on the Newtown Loop

Zone 2

September 12, 2017

Approx. 12 hours

Not expected to affect Transportation/Loan Availability.

Croghan  Annual Compressor and Station Maintenance

Zone 1 and Zone 2

September 11, 2017 –

September 16, 2017

12 hours each day.

May affect Primary Firm, Secondary, and IT Transportation/Loan Availability.

Dover Annual Compressor and Station Maintenance

Zone 2

September 18, 2017 – September 30, 2017

24 hours each day.

May affect Primary Firm, Secondary, and IT Transportation/Loan Availability.

Athens Annual Compressor and Station Maintenance

Zone 2

October 2, 2017 – October 6, 2017

Approx. 12 hours each day.

May affect IT and Secondary Transportation/Loan Availability.

Milford Annual Compressor and Station Maintenance

Zone 2

October 9, 2017 – October 13, 2017

Approx. 12 hours each day.

May affect IT and Secondary

Transportation/Loan Availability.

Brookfield Annual Compressor and Station Maintenance

Zone 2

March 26, 2018 – March 30, 2018

Approx. 12 hours each day.

May affect Primary Firm, Secondary, and IT Transportation Loan Availability.

*Carryover information from the 2016-2017 Annual Maintenance posting.         

 4/19/2017

 

 Notice End Date/Time:  04/01/2018 09:00:00
 Reqrd Rsp Desc: No Response Required
 Response Date/Time:  
 Posting Date/Time:  04/19/2017 15:48:00
 Contacts:  Esposito, John - (203) 944 - 7028