Your Access to Gas Pipeline Notices

These gas pipeline notices may be of interest to our customers. Feel free to contact us if you should have any questions or comments relating to this information.


 Notice Status Description:   Initiate
 Prior Notice Identifier:  
 Notice Type Description:  Maintenance
 Critical?:  N
 Notice Effective Date/Time:  04/01/2010 09:00:00
 Subject:  April 2010-March 2011 Annual Maintenance
 Notice Text:
  Pursuant to section 20

Pursuant to section 20.2a of the Iroquois Gas tariff, listed below are the maintenance projects that are scheduled for the year beginning April 1, 2010 and ending March 31, 2011.

Project Description

Affected Area

Outage Time

Duration

Impact

Boonville Annual Compressor Maintenance

Zone 1 and Zone 2

April 12 – April 15

Approx. 12 hours each day

May affect IT and Secondary Transportation/Loan Availability

Dover Annual Compressor Maintenance

Zone 2

April 19 – April 23

Approx. 12 hours each day

May affect IT and Secondary Transportation/Loan Availability

Brookfield Annual Compressor Maintenance

Zone 2

May 3  – May 7

Approx. 12 hours each day

May affect Primary Firm, Secondary and IT Transportation/Loan Availability  Receipts at the Brookfield Compressor Station

Wright Annual Compressor Maintenance

Zone 2

May 10 – May 14

Approx. 12 hours each day

May affect IT and Secondary Transportation/Loan Availability

Athens Annual Compressor Maintenance

Zone 2

May 17 – May 19

Approx. 12 hours each day

May affect IT and Secondary Transportation/Loan Availability

Athens Annual Compressor Maintenance (CY15)

Zone 2

September 13 – September 15

Approx. 12 hours each day

May affect IT and Secondary Transportation/Loan Availability

Wright Compressor A1 Changeout

Zone 2

September 20 – September 25

24 hours each day

May affect IT and Secondary Transportation/Loan Availability

Wright Compressor A2 Changeout

Zone 2

September 27 – October 2

24 hours each day

May affect IT and Secondary Transportation/Loan Availability

Croghan Annual Compressor Maintenance

Zone 1 and Zone 2

October 4 - October 8

Approx. 12 hours each day

May affect IT and Secondary Transportation/Loan Availability

Dover GG Changeout

Zone 2

October 11 – October 18

24 hours each day

May affect IT and Secondary Transportation/Loan Availability

Milford Annual Compressor Maintenance

Zone 2

October 25 – October 29

Approx. 12 hours each day

May affect IT and Secondary

Transportation/Loan Availability

Additional details and exact times of these projects will be communicated via maintenance bulletins as the target dates near.

 Notice End Date/Time:  04/01/2011 09:00:00
 Reqrd Rsp Desc: No Response Required
 Response Date/Time:  
 Posting Date/Time:  03/19/2010 12:39:56
 Contacts:  Control, Gas - (203) 925 - 7212
 Notice Identifier:  2043